Schedules

PhysicISOLDE Physics Schedule | Project CERN-0000224856

https://isolde.web.cern.ch/weekly-schedules

 
Detailed schedule: https://cernbox.cern.ch/s/ck3wY5JYyZWiu5G

This is kept up to date, so you can refer to it if you have questions about the plans beyond the weekly schedule sent out on Fridays.
Overview schedule for quick reference: https://isolde.web.cern.ch/isolde-schedule-2025

Schedule on EDMS: https://edms.cern.ch/document/3289042/1

beam requests
2024/11/25
Last protons to ISOLDE (338th IEFC meeting)
2024/12/09
Winter physics ends
2024/12/12
Lock in
2024/12/19
 Water stopped
 
 
2025/01/11
Test Annuel Arrêts d’Urgence (AUG) MEYRIN ZONE PS/BOOSTER
2025/02/18
Start of Target, Low E and HIE ISOLDE HW Commissioning
2025/02/24
Water back to ISOLDE
2025/02/25
Rota starts: IMS1 & IMS2, NO stand-by service
2025/02/25-26
BTY line tests
2025/03/05
Start of Target and Low E Beam commissioning
2025/03/07
DSO test (edms 2681121/2025
)
ISOLDE Target – Beam Permit EDMS 1132631 to be approved before 2025/03/10
2025/03/07
DSO tests
REX/HIE-ISOLDE – RF Permit EDMS 1686095 to be approved before 11/03/2025
Cooldown of the Cryo Modules
HIE-ISOLDE – Beam Permit to be approved EDMS 1703483 before 21/04/2025
2024/03/18
Stand-by service starts
2025/03/21
First protons to ISOLDE (357th IEFC meeting)
 
 
20/03-24/03
24/03-28/03
24.03: Installation of SEMgrid target in the GPS front-end
26.03: Target ready for first protons
01.04: SEMgrid target removed from GPS front-end and installed in HRS front-end 
02.04: SEMgrid target from HRS front-end
3rd or 4th of April
MEDICIS tests gafchromic verify parameters used for direct irradiation
2025/03/28
Low energy physics starts
2025/04/22 (21?)
Start of HIE-ISOLDE beam commissioning
2025/06/13
Physics start HIE-ISOLDE
2025/12/08
Last protons to ISOLDE (357th IEFC meeting)
2025/12/16
Stand-by service starts
YETS2024-2025
 (EDMS3074458) 25/11/24 – 07/03/25

https://indico.cern.ch/event/1305334/
REX-HIE ISOLDE YETS 24/25 planning | Document 3182746
Isolde Target area/ Separator zones YETS  planning EDMS 2961471

EN-EL tests
https://edms.cern.ch/ui/file/3121856/1.0/Electrical_test_during_EYETS_2425_2024-10-01_pptx_cpdf.pdf





YETS2025-2026
Injectors Schedulehttps://beams.web.cern.ch/accelerators-and-schedules
https://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/default.aspx

Injectors: 2025: https://edms.cern.ch/document/3057281/0.1
[CERN-JIRA] (CPSSAFETY-136) Re: [2025 DSO test] ISOLDE – planning DSO tests planning DSO tests https://edms.cern.ch/document/2681121/2025
Injectors: 2024: https://edms.cern.ch/document/2872566/2.0
Injectors Schedule 2023 EDMS2785499,
2022 EDMS244555
2021 EDMS 2442568 and in indico 932569,
2018 EDMS1882670 archives 2017, 2016, 2015,..
Long Term ScheduleLong Term Schedule for the CERN Accelerator Complex EDMS2311633

Accelerator Schedule Management ASM

Accelerators Master Schedules CERN-0000205174

http://lhc-commissioning.web.cern.ch/
ArchivesLS2 Master Schedule https://edms.cern.ch/document/ACC-PM-MS-0002
Injectors Schedule 2022 (Draft version) EDMS2664482, 2021 EDMS2442568, 2018 EDMS1882670,  archives 2
2021 Recommissioning plan with the detailed dates EDMS 2477307

ISOLDE timelines